Hoboken commuters rejoice - riders can expect to see some upgrades after a 25-day closure of the Hoboken PATH station.
PATH says the near monthlong closure addressed critical repairs.
During the first week of the station's closure, they focused on destruction, decluttering and blasting away the old infrastructure.
RELATED: Hoboken PATH station to reopen Tuesday after monthlong renovation
RELATED:Track and station upgrade work begins at Hoboken PATH station
By week 2, a new track and new features were installed, including wider staircases and a massive track switch.
During week 3, cosmetic improvements were done, like new concrete surfaces and tiling.
PATH says the construction is part of the agency’s two-year $430 million PATH Forward program.