The Gateway Development Commission announced Tuesday that a second tunnel boring machine has begun excavating the southern tube of the Hudson Tunnel Project, meaning construction is now underway on both of the new rail tunnel's tubes.
The first machine began work on the northern tube in October. Together, the machines are excavating the first 5,100 feet of tunnel in New Jersey between North Bergen and the Hudson County Access Shaft near the border of Hoboken and Weehawken.
READ MORE: Gateway Tunnel blasting begins in Hudson County next week; test blasting set for Wednesday
According to the commission, that phase of tunnel construction is expected to take about one year, including scheduled maintenance pauses. Once completed, the machines will be removed and replaced with another pair designed to tunnel beneath the Hudson River.
READ MORE: Gateway Project begins burrowing new NJ-NYC train tunnel
READ MORE: Toll of Commuting: A hands-on look at where the Hudson Tunnel Project stands
The machine building the northern tunnel has already advanced about 400 feet and installed more than 60 rings of tunnel lining, according to the commission.
The Hudson Tunnel Project is divided into 10 construction packages. The current tunneling work is part of the Palisades Tunnel Project, which is being built by Schiavone Lane Dragados JV and managed by the Port Authority of New York and New Jersey in partnership with the Gateway Development Commission.